Working with us

Our professional labor and management team have over twenty years of experience in all phases of demolition, asbestos and lead abatement to assure you of a controlled project completed in a safe and timely manner. Trained, certified and licensed asbestos personnel perform all of Turbo Group operations.

The following outline provides additional information in order to better understand our company and services:


1. SALES CONSULTANTS

Our sales people are highly trained and certified in demolition and asbestos removal procedures and offer the most cost effective and safest procedures of demolition and asbestos removal for our clients. Turbo Group, Inc. is exceptionally keen at identifying and assessing problem areas while offering various solutions in a professional, understandable format. Our remedial programs are custom made to fit our clients’ needs.

Working with Turbo Group
2. PROJECT MANAGEMENT

Our management team of supervisors and workers are experienced and licensed professionals. Along with a thorough understanding of the demolition and asbestos and lead industry, each team specializes in a specific area. From the pre-construction meeting to permit application to final completion, each project is carefully planned and scheduled according to our client’s needs.

3. FIBER CONTROL PROGRAM

Our Fiber Control Program was designed specifically for tradesmen to service routine mechanical problems or renovations in buildings, which contain asbestos materials. Now tradesmen can safely and efficiently work around asbestos and still get the job done. This program involves Turbo Group supplying personal protection and engineering controls with different stages of protection for tradesmen. This will allow you to open ceilings, pull wires, and service HVAC units with the reduced potential threat of contamination.

Different stages of control measures are listed below, which provide you with different degrees of protection. The nature of work and asbestos-containing material present will dictate the proper stage to be utilized.

Stage 1

Stage 1 involves minor work with friable asbestos-containing materials. Stage 1 includes general maintenance activities or service and renovation activities that may have to open ceilings and/or work near asbestos-containing material. Stage 1 does not involve the removal or disturbance of asbestos-containing materials.

Turbo Group will use localized HEPA vacuuming and HEPA filtration units to control any potential fallout. The intent is to maintain building air quality and to prevent exposure to building occupants.

Stage 2

Stage 2 involves any activity, which might dislodge or disturb the asbestos material. Work, such as core drilling, trenching, or shooting metal fasteners into the ceiling deck and on beams would constitute a stage 2 setup. In addition, any spot removal or ceiling tile removal would apply. Stage 2 entails the same utilization of equipment as Stage 1 with some important additional engineering and quality control measures:

1. We will in this case place polyethylene sheeting on the floor under the work area and/or provide ceiling manifolds for work above the drop ceiling.

2. All personnel actively working with any removal operations shall also wear an approved air-purifying respirator.

3. The air handling system (HVAC) feeding that particular zone must be shut down or sealed. The HVAC unit should not be activated until final (post-sampling) air concentrations are reviewed and found acceptable. Temporary blanking or sealing of the system may be acceptable if approved by the Project Manager and the attending Industrial Hygienist.

4. Make available engineering controls (i.e., airborne levels).

5. All accumulations of wet cuttings, asbestos dusts or HEPA vacuum units shall clean up other debris and the area will be washed with water if necessary.

6. All debris shall be disposed of as contaminated in labeled 6-mil polyethylene bags.

Stage 3

Stage 3 is a full-scale asbestos removal project. Turbo Group, Inc., uses the same methods described in Stages 1 and 2, except that this procedure encompasses total isolation, temporarily evacuation of that floor, complete prepping of floors, walls, HVAC units, ducts, windows, and decontamination units.

4. LEGAL FOLDER

Turbo Group, Inc. provides our clients with all pertinent information needed to document the project. This will help to protect you from incurring any further liabilities related to the project.
Our package certifies the project complete per specifications in accordance to federal, state and local regulations. The submittals shall include:

a. Work specifications and procedures.
b. Copies of all notifications to appropriate agencies.
c. Asbestos insurance certificates.
d. Copy of Turbo Group, Inc., asbestos license.
e. Copy of asbestos hauling permit.
f. Copy of asbestos waste manifest at approved dumpsite.
g. All pertinent air monitoring analysis results.